September 27, 2019 - Construction Update

The contractor began construction of the Route 123 Sidewalk Improvements on May 1, 2019.


During the week of September 21 – September 27 the Contractor:

  • Began back fill and drainage placement on the backside of Retaining Wall #4

  • Continued masonry brick work on Retaining Wall #4

  • Completed rebar placement and concrete pour for footer on Retaining Wall #1


Activities planned for the week of September 28 – October 4 include:

  • Continuing CMU block installation for retaining wall #2 along Chain Bridge Road

  • Begin excavation services for Retaining Wall #1 and brick fence wall along Chain Bridge Road

  • Continuing masonry brick work on Retaining Walls #4 and #3

  • Begin mobilizing to start post and panel wall




Please note this schedule is subject to change due to inclement weather. ​


Back fill and drainage placement on the backside of Retaining Wall #4

Rebar placement and concrete footer on Retaining Wall #1