September 20, 2019 - Construction Update

The contractor began construction of the Route 123 Sidewalk Improvements on May 1, 2019.


During the week of September 14 – September 20 the Contractor:

  • Continued installation of storm drainage structures along Chain Bridge Road

  • Completed tree removal services along Chain Bridge Road

  • Began excavation services for temporary benching for post and panel walls along Chain Bridge Road

  • Began conduit placement for Retaining Wall #4

  • Began masonry brick work on Retaining Wall #4


Activities planned for the week of September 21 – September 27 include:

  • Continuing CMU block installation for retaining walls #4, #3, & #2 along Chain Bridge Road

  • Continuing excavation services for temporary benches for post and panel walls along Chain Bridge Road




Please note this schedule is subject to change due to inclement weather. ​


Tree Services along Chain Bridge Road

Continuing storm structure installation along Chain Bridge Road