September 13, 2019 - Construction Update

The contractor began construction of the Route 123 Sidewalk Improvements on May 1, 2019.


During the week of September 07 – September 13 the Contractor:

  • Continued installation of storm drainage structures along Chain Bridge Road

  • Continued installing CMU block for retaining wall #4 along Chain Bridge Road


Activities planned for the week of September 14 – September 20 include:

  • Continuing CMU block installation for retaining walls #4, #3, & #2 along Chain Bridge Road

  • Beginning tree removal for remaining trees along Chain Bridge Road

  • Starting construction of temporary benches for post and panel walls




Please note this schedule is subject to change due to inclement weather. ​


Installation of storm drainage structures along Chain Bridge Road

CMU block installation for retaining wall #4 along Chain Bridge Road