September 06, 2019 - Construction Update

The contractor began construction of the Route 123 Sidewalk Improvements on May 1, 2019.


During the week of August 31 – September 06 the Contractor:

  • Completed placement and tying of reinforcing steel for retaining walls #2 and #3 along Chain Bridge Road

  • Completed the concrete pour for the foundations of retaining walls #2, #3, and #4 along Chain Bridge Road

  • Installed and set storm drainage structure 3-6 along Chain Bridge Road

  • Began installing CMU block for retaining wall #4 along Chain Bridge Road


Activities planned for the week of September 07 – September 13 include:

  • Begin excavation for the foundation for retaining wall #1 along Chain Bridge Road

  • Begin placement and tying of reinforcing steel for retaining wall #1 along Chain Bridge Road

  • Begin concrete pour for foundation of retaining wall #1 along Chain Bridge Road

  • Begin installing CMU block for retaining walls #2 and #3 along Chain Bridge Road



Please note this schedule is subject to change due to inclement weather. ​


Concrete pour for foundations of retaining walls #2, #3 & #4 along Chain Bridge Road

Installed and set storm drainage structure 3-6 along Chain Bridge Road