October 18, 2019 - Construction Update

The contractor began construction of the Route 123 Sidewalk Improvements on May 1, 2019.


During the week of October 12 – October 18 the Contractor:

  • Continued masonry block and decorative brick installation

  • Began excavation and reconstruct of existing sanitary sewer line along Chain Bridge Road

  • Began underdrain installation along Chain Bridge Road


Activities planned for the week of October 19 – October 25 include:

  • Continuing CMU block installation

  • Continuing decorative brick work installation

  • Continuing underdrain installation

  • Begin drilling and back fill for post and panel walls



Please note this schedule is subject to change due to inclement weather. ​


Continued masonry block and decorative brick installation

Reconstruct of existing sanitary sewer line along Chain Bridge Road