October 04, 2019 - Construction Update

The contractor began construction of the Route 123 Sidewalk Improvements on May 1, 2019.


During the week of September 28 – October 04 the Contractor:

  • Mobilized drill equipment, and materials for post and panel retaining wall placement along Chain Bridge Road

  • Continued masonry block and decorative brick installation

  • Began brick fence A excavation and reinforcing steel placement


Activities planned for the week of October 05 – October 11 include continuing:

  • CMU block installation

  • Decorative brick work installation

  • Excavation services for retaining walls and brick fence along Chain Bridge Road



Please note this schedule is subject to change due to inclement weather. ​


Continued masonry block and decorative brick installation

Reinforcing steel placement for brick fence