November 29, 2019 - Construction Update

The contractor began construction of the Route 123 Sidewalk Improvements on May 1, 2019.


During the week of November 23 – November 29 the Contractor:

  • Continued masonry block and decorative brick installation

  • Continued back fill of retaining wall and brick fence along Chain Bridge Road

  • Began excavation of granite curb placement along Chain Bridge Road



Activities planned for the week of November 30 – December 06 include:

  • Continuing CMU block and decorative brick work installation

  • Continuing granite curb placement




Please note this schedule is subject to change due to inclement weather. ​


Excavation of granite curb placement

Continued decorative brick placement along Chain Bridge Road