November 08, 2019 - Construction Update

The contractor began construction of the Route 123 Sidewalk Improvements on May 1, 2019.


During the week of November 02 – November 08 the Contractor:

  • Continued masonry block and decorative brick installation

  • Continued back fill of retaining wall and brick fence along Chain Bridge Road

  • Continued drilling and pouring for post and panel retaining wall piles

  • Graded and formed for 4" concrete sidewalk for underlayment for brick sidewalk to be placed on a later date

  • Began masonry block placement for brick fence

  • Continued underdrain installation along Chain Bridge Road


Activities planned for the week of November 09 – November 15 include:

  • Continuing CMU block and decorative brick work installation

  • Continuing decorative brick work installation

  • Begin 2" electrical conduit installation

  • Continuing drilling, setting piles, and back fill for post and panel walls



Please note this schedule is subject to change due to inclement weather. ​


Drilling and pouring for piles for post and panel retaining wall

Continued underdrain installation along Chain Bridge Road