May 22, 2020 - Construction Update

The contractor began construction of the Route 123 Sidewalk Improvements on May 1, 2019.


During the week of May 16 – May 22 the Contractor:


  • Continued installation of decorative brick placement for Brick Fence B and Brick Sidewalk

  • Performed general site cleanup along Chain Bridge Road

  • Continued installation of junction boxes for Street Lighting along Chain Bridge Road

  • Continued excavation, forming, and tied reinforcing steel for the Pedestrian Safety Barrier along SB Rte. 123



Activities planned for the week of May 23 – May 29 include:


  • Begin excavation of footings and placement of rebar for Concrete barrier wall

  • Begin installation of concrete footings and install lights for light poles and retaining walls 1-4



Please note this schedule is subject to change due to inclement weather. ​


Continued placement of brick pavers along Chain Bridge Road



Continued excavation, forming, and tied reinforcing steel for the Pedestrian Safety Barrier along Chain Bridge Road