May 17, 2019 - Construction Update

The contractor began construction of the Route 123 Sidewalk Improvements on May 1, 2019.


During the week of May 13 – May 17 the Contractor:

Contractor mobilized equipment and traffic control devices

  • Continued excavating and installed 280 LF of 8-DI water main along Chain Bridge Road

  • Continued erosion and sediment control measures

  • Continued staging two flaggers at the front entrances for residents at the Mews during rush hour traffic Monday-Friday on University Drive and Whitehead during the hours of 7:00-9:00 AM

  • Had RE Lee Electric onsite for utility relocation

Activities planned for the week of May 20 – May 24 include:

  • Begin concrete barricade installation

  • Continue water main installation

  • Begin cutting trees along Chain Bridge Road


Please note this schedule is subject to change due to inclement weather. ​

Backfill Compaction for Water Main

Water Main Installation