May 08, 2020 - Construction Update

The contractor began construction of the Route 123 Sidewalk Improvements on May 1, 2019.


During the week of May 02 – May 08 the Contractor:


  • Continued installation of masonry block and decorative brick placement for Brick Fence B

  • Continued installation of storm drain structure along Chain Bridge Road

  • Performed general site cleanup along Chain Bridge Road

  • Began foundations for Street Lighting along Chain Bridge Road



Activities planned for the week of May 09 – May 15 include:


  • Continuing installation of masonry block and decorative brick placement for Brick Fence B

  • Continuing placement of UD-3, UD-4 and electrical conduit along Chain Bridge Road

  • Begin excavation of footings and placement of rebar for Concrete barrier wall

  • Begin installation of concrete footings and install lights for light poles and retaining walls 1-4




Please note this schedule is subject to change due to inclement weather. ​


Began foundations for Street Lighting along Chain Bridge Road



Continued installation of storm drain structure along Chain Bridge Road