March 13, 2020 - Construction Update

Updated: Apr 11

The contractor began construction of the Route 123 Sidewalk Improvements on May 1, 2019.


During the week of March 07 – March 13 the Contractor:


  • Continued installation of masonry block and decorative brick placement for Post and Panel Wall #5 and the Mod. RW-3 retaining wall #6

  • Continued brick placement and finish grouting along angle iron for the Brick sidewalk

  • Continued to reset grade of UD-3 stone and set forms in preparation for 4" concrete sidewalk underlayment pouring for the Brick Sidewalk



Activities planned for the week of March 14 – March 20 include:


  • Continuing footing excavation and form and pour concrete of Brick Fence B

  • Continuing installation of masonry block and decorative brick placement for Brick Fence B

  • Begin installation of brick pavers for Post and Panel Wall




Please note this schedule is subject to change due to inclement weather. ​


Continued preparation of brick pavers for Brick Sidewalk



Continued installation of masonry block and decorative brick placement for Post and Panel Wall