June 21, 2019 - Construction Update

The contractor began construction of the Route 123 Sidewalk Improvements on May 1, 2019.


During the week of June 15 – June 21 the Contractor:

  • Completed installation of new water main tie-ins to the existing water main at multiple locations along Chain Bridge Road

  • Began additional water main installation at the intersection of North Street and Chain Bridge Road

Activities planned for the week of June 22 – June 28 include:

  • Begin chain link fence installation

  • Begin water main flushing and testing of the additional water main with Fairfax Water observing at the intersection of North Street and Chain Bridge Road


Please note this schedule is subject to change due to inclement weather. ​


Installation of additional water main

Trench backfill of additional water main at North Street and Chain Bridge Road