June 12, 2020 - Construction Update

The contractor began construction of the Route 123 Sidewalk Improvements on May 1, 2019.


During the week of June 06 – June 12 the Contractor:


  • Continued installation of decorative brick placement for Brick Sidewalk

  • Performed general site cleanup along Chain Bridge Road

  • Continued pouring concrete sidewalk, pedestrian ramp, and curb and gutter at intersection of Rt. 123 and Rust Hill Place

  • Performed final grading, topsoil, grass seed, and straw mat placement for restoration throughout site.

  • Continued installation of junction boxes, conduit, streetlight pole foundations for street lighting, retaining wall lighting and brick fence up lighting along Chain Bridge Road



Activities planned for the week of June 13 – June 19 include:


  • Continued installation of bricks for sidewalk along Chain Bridge Road

  • Begin installation of lights along Chain Bridge Road

  • Begin landscaping



Please note this schedule is subject to change due to inclement weather. ​


Performed final grading, topsoil, grass seed, and straw mat placement for restoration throughout site.



Continued pouring concrete sidewalk, pedestrian ramp, and curb and gutter at intersection of Rt. 123 and Rust Hill Place