July 5, 2019 - Construction Update

The contractor began construction of the Route 123 Sidewalk Improvements on May 1, 2019.


During the week of June 29 – July 5 the Contractor:

  • Continued installation of the water service lines on Chain Bridge Road

  • Began removing exterior brick wall


Activities planned for the week of July 6 – July 12 include:

  • Beginning storm water sewer installation

  • Continuing tree removal services


Please note this schedule is subject to change due to inclement weather. ​


Removal of existing brick wall

Installation of water service line