July 26, 2019 - Construction Update

The contractor began construction of the Route 123 Sidewalk Improvements on May 1, 2019.


During the week of July 20 – July 26 the Contractor:

  • Continued storm water sewer installation

  • Continued demolition of existing brick wall along Chain Bridge Road

  • Installed two right turn arrows between Main Street and North Street on NB Chain Bridge Road

  • Installed nineteen yellow delineators at various locations along Chain Bridge Road

  • Continued tree removal services


Activities planned for the week of July 27 – August 02 include:

  • Continuing storm water sewer installation

  • Continuing tree removal services

  • Begin excavating foundations for retaining wall installation along Chain Bridge Road


Please note this schedule is subject to change due to inclement weather. ​


Storm water pipe installation

Right turn arrows installed between Main Street and North Street