July 19, 2019 - Construction Update

Updated: Aug 29, 2019

The contractor began construction of the Route 123 Sidewalk Improvements on May 1, 2019.


During the week of July 13 – July 19 the Contractor:

  • Continued storm water sewer installation

  • Completed installation of additional water main tie-ins to existing water main along Chain Bridge Road and North Street


Activities planned for the week of July 20 – July 26 include:

  • Continuing storm water sewer installation

  • Continuing tree removal services


Please note this schedule is subject to change due to inclement weather. ​


Storm water pipe installation

Excavation for storm water pipe installation