July 12, 2019 - Construction Update

The contractor began construction of the Route 123 Sidewalk Improvements on May 1, 2019.


During the week of July 6 – July 12 the Contractor:

  • Began storm water sewer installation


Activities planned for the week of July 13 – July 19 include:

  • Continuing installation of new additional water main tie-ins to existing water main along Chain Bridge Road and North Street

  • Continuing tree removal services


Please note this schedule is subject to change due to inclement weather. ​


Storm water pipe installation

Storm water structure installation