January 24, 2020 - Construction Update

Updated: Apr 11

The contractor began construction of the Route 123 Sidewalk Improvements on May 1, 2019.


During the week of January 18 – January 24 the Contractor:

  • Continued forming, stone placement, and reinforcing steel placement for Brick Fence B

  • Continued installation of brick pavers and paver restraints for sidewalk

  • Continued installation and back fill of concrete panels



Activities planned for the week of January 25 – January 31 include:

  • Continuing installation of concrete panels

  • Continuing footing excavation and form and pour concrete of Brick Fence B

  • Continuing installation of brick pavers for sidewalk




Please note this schedule is subject to change due to inclement weather. ​


Continued installation and back fill of concrete panels



Installation of paver restraints for brick sidewalk