January 17, 2020 - Construction Update

Updated: Apr 11

The contractor began construction of the Route 123 Sidewalk Improvements on May 1, 2019.


During the week of January 11 – January 17 the Contractor:

  • Continued forming, stone placement, and reinforcing steel placement for Brick Fence B

  • Began installation of brick pavers for sidewalk

  • Began installation of concrete panels

  • Began installation of the stacked stone wall tien in for retaining wall #1

  • Reinstalled delineators along Chain Bridge Road


Activities planned for the week of January 18 – January 24 include:

  • Continuing installation of concrete panels

  • Continuing footing excavation and form and pour concrete of Brick Fence B

  • Continuing installation of stone top caps on Retaining Walls #1-#4

  • Begin installation of electrical conduit and footings

  • Continuing installation of brick pavers for sidewalk




Please note this schedule is subject to change due to inclement weather. ​


Began installation of brick pavers for sidewalk



Reinstalled delineators along Chain Bridge Road