January 10, 2020 - Construction Update

Updated: Apr 11

The contractor began construction of the Route 123 Sidewalk Improvements on May 1, 2019.


During the week of January 04 – January 10 the Contractor:

  • Began excavation, forming, stone placement, and reinforcing steel placement for Brick Fence B

  • Began installation of stone top caps on retaining walls

  • Began preliminary layout of brick sidewalk in front of retaining wall #1

  • Continued cleaning, forming, and pouring concrete pile haunches for post and panel retaining wall #5

  • Began installation of Geo textile fabric on lagging boards for post and panel retaining wall #5

  • Removed existing privacy fence and installed chain link construction fence along SB Rte. 123 in preparation for installation of Brick Fence B


Activities planned for the week of January 11 – January 17 include:

  • Begin installation of concrete panels

  • Continuing footing excavation and form and pour concrete of Brick Fence B

  • Continuing installation of stone top caps on Retaining Walls #1-#4

  • Begin installation of electrical conduit and footings

  • Begin installation of brick pavers for sidewalk




Please note this schedule is subject to change due to inclement weather. ​


Began preliminary layout of brick pavers for brick sidewalk



Continued forming, and pouring concrete pile haunches for post and panel retaining wall #5