January 03, 2020 - Construction Update

Updated: Apr 11

The contractor began construction of the Route 123 Sidewalk Improvements on May 1, 2019.


During the week of December 28 – January 03 the Contractor:

  • Began test pit existing utilities to prepare for excavation of foundation of Brick Fence B

  • Began installation of stone top caps on Retaining Walls #1 and #2

  • Removed forms and began porous back fill of Retaining Wall #6

  • Began placement of concrete haunches in preparation for future concrete panel placement of post and panel Retaining Wall #5



Activities planned for the week of January 04 – January 10 include:

  • Begin installation of concrete panels

  • Begin footing excavation and form and pour concrete of Brick Fence B

  • Continuing installation of stone top caps on Retaining Walls #1-#4

  • Prepare leveling pad for concrete panels

  • Begin installation of brick pavers for sidewalk




Please note this schedule is subject to change due to inclement weather. ​


Began installation of stone top caps on Retaining Walls #1 and #2


Backfilling of Retaining Wall #6