February 21, 2020 - Construction Update

Updated: Apr 11

The contractor began construction of the Route 123 Sidewalk Improvements on May 1, 2019.


During the week of February 15 – February 21 the Contractor:

  • Continued forming, stone placement, and reinforcing steel placement for Brick Fence B

  • Excavated, formed, placed conduit for drainage and lighting, and poured concrete for Retaining Wall #7

  • Continued installation of brick pavers for sidewalk

  • Began cutting and welding angle iron shelves for Retaining Wall #5



Activities planned for the week of February 22 – February 28 include:

  • Continuing footing excavation and form and pour concrete of Brick Fence B

  • Continuing installation of brick pavers for sidewalk

  • Begin installation of brick pavers for Brick Fence Wall B and Post and Panel Wall




Please note this schedule is subject to change due to inclement weather. ​