The contractor began construction of the Route 123 Sidewalk Improvements on May 1, 2019.


During the week of December 21 – December 27 the Contractor:

  • Began footing excavation and form and pour concrete of Retaining Wall #6

  • Began base preparation of concrete panels

  • Project site cleanup



Activities planned for the week of December 28 – January 03 include:

  • Begin installation of concrete panels

  • Begin footing excavation and form and pour concrete of Brick Fence B