December 06, 2019 - Construction Update

The contractor began construction of the Route 123 Sidewalk Improvements on May 1, 2019.


During the week of November 30 – December 06 the Contractor:

  • Continued masonry block and decorative brick installation

  • Began excavation and placement of 2" PVC conduit for street lighting

  • Continued excavation and installation of granite curb along Chain Bridge Road



Activities planned for the week of December 07 – December 13 include:

  • Continuing CMU block and decorative brick work installation

  • Continuing granite curb installation

  • Begin lagging and back fill of post and panel walls

  • Begin installation of electrical conduit and wires for retaining walls #1 - #4




Please note this schedule is subject to change due to inclement weather. ​


Granite curb installation and placement

Continued decorative brick placement along Chain Bridge Road