The contractor began construction of the Route 123 Sidewalk Improvements on May 1, 2019.


During the week of August 17 – August 23 the Contractor:

  • Continued placement and tying of reinforcing steel for retaining wall #4 along Chain Bridge Road

  • Began concrete pour for footers of retaining wall #4 along Chain Bridge Road


Activities planned for the week of August 24 – August 30 include:

  • Begin placement and tying of reinforcing steel for retaining walls #3 and #2 along Chain Bridge Road

  • Begin excavation for foundations for retaining walls #3 and #2 along Chain Bridge Road


Please note this schedule is subject to change due to inclement weather. ​


Continued placement and tying of Reinforced Steel for Retaining Wall #4 along Chain Bridge Road

Began concrete pour for footers of retaining wall #4 along Chain Bridge Road