August 02, 2019 - Construction Update

The contractor began construction of the Route 123 Sidewalk Improvements on May 1, 2019.


During the week of July 27 – August 02 the Contractor:

  • Completed storm water sewer installation

  • Continued tree removal services

  • Began excavating foundations for retaining wall installation along Chain Bridge Road


Activities planned for the week of August 03 – August 09 include:

  • Continuing excavation of foundations for retaining wall installation along Chain Bridge Road

  • Begin retaining wall installation along Chain Bridge Road


Please note this schedule is subject to change due to inclement weather. ​


Tree Removal Services along Chain Bridge Road

Storm water sewer installation