April 24, 2020 - Construction Update

The contractor began construction of the Route 123 Sidewalk Improvements on May 1, 2019.


During the week of April 18 – April 24 the Contractor:


  • Continued installation of masonry block and decorative brick placement for Brick Fence B

  • Continued installation of 2" PVC Conduit for future installation of street lighting

  • Continued placement of storm drain crossing along Chain Bridge Road

  • Continued placement of PVC pipe for drainage restoration

  • Performed general cleanup along Chain Bridge Road



Activities planned for the week of April 25 – May 01 include:


  • Continuing installation of masonry block and decorative brick placement for Brick Fence B

  • Continuing placement of UD-3, UD-4 and electrical conduit along Chain Bridge Road

  • Begin excavation of footings and placement of rebar for Concrete barrier wall




Please note this schedule is subject to change due to inclement weather. ​